Update on Timing and Contents of the New Act Governing Permitting and Construction of Offshore Wind Power within the Finnish EEZ

D&I Alert

Posted on

2 Feb

2024

Dittmar & Indrenius > Insight > Update on Timing and Contents of the New Act Governing Permitting and Construction of Offshore Wind Power within the Finnish EEZ

In November 2023, the Finnish Ministry of Economic Affairs and Employment (the “MEE“) appointed a working group tasked to prepare a new act (the “Act“) that will govern permitting and construction of offshore wind power within Finland’s exclusive economic zone (the “Finnish EEZ“)1. The MEE has now published an updated estimate on the timing of the legislative process as well as outlined a number of key elements of the contemplated Act.

Timing

  • Discussions between stakeholders (including project developers) and the working group take place during February 2024.
  • A draft government proposal regarding the Act is planned to be circulated for comments during May 2024.
  • The finalised government proposal is planned to be issued to the Finnish Parliament during fall 2024.
  • The Act will enter into force on 1 January 2025 at the earliest.

Key Elements of the Contemplated Act

Under the Act, the Finnish Government will retain its authority to decide which project areas located in the Finnish EEZ will be auctioned. The MEE will be responsible for ensuring that the planning of the project areas offered for auction is reconciled with the maritime spatial plan as well as that construction at the selected project areas is in the best interests of the society. Either the Finnish Energy Authority or, alternatively, Metsähallitus2 is currently envisaged to be appointed the entity responsible for arranging the auction process. Quality and pricing (i.e., fees paid to the State of Finland during production) will form the key criteria that is considered when selecting the auction winner. The winner will be granted an exploitation permit granting exclusive rights to research, exploit and specify the area for which permits required for construction of individual WTGs will be applied for. The Act is also envisaged to contain specific provisions for obtaining construction permits within the Finnish EEZ. This is because the new Finnish Construction Act, which will enter into force on 1 January 2025, does not in its current form apply to areas located within the Finnish EEZ.

The applicability of Finnish tax laws in the Finnish EEZ is currently being analysed by the Finnish Ministry of Finance. The outcome of the analysis could have effect on, among other things, structuring of offshore wind projects and investments. The applicability of Finnish employment legislation and legislation relating to waste management, rescue matters, electricity and gas markets as well as chemical safety in the Finnish EEZ is also currently under consideration. Moreover, the MEE is also considering whether it would be possible to include specific provisions regarding construction of hydrogen plants within the Finnish EEZ to the Act.

According to the MEE, no exploitation permit applications requesting for site exclusivity that have already been submitted to the Finnish Government have been so far approved. The MEE has not published any information regarding the timing for processing these permit applications.

Contacts

We are actively monitoring all legislative developments affecting the Finnish onshore and offshore wind sector and would be pleased to discuss any questions that you may have.

 

1 New Act Governing Permitting and Construction of Offshore Wind Power within the Finnish EEZ Under Preparation – Dittmar & Indrenius

2 Metsähallitus is a state-owned enterprise that manages land and water areas owned by the State of Finland and reconciles different goals of landowners, customers and other stakeholders. Metsähallitus is responsible for, among other things, arranging auction processes for project areas located within Finnish territorial waters.

More by the same author

Upcoming New Act Governing Permitting and Construction of Offshore Wind Power within the Finnish EEZ

In November 2023, the Finnish Ministry of Economic Affairs and Employment (the “MEE“) appointed a working group tasked to prepare a new act (the “Act“) that will govern permitting and construction of offshore wind power within Finland’s exclusive economic zone (the “Finnish EEZ“)1. The MEE has now published an updated estimate on the timing of the legislative process as well as outlined a number of key elements of the contemplated Act.

Vastuullisuus yrityskaupoissa

Dittmar & Indreniuksen laatima uusi opas “Vastuullisuus yrityskaupoissa” tarjoaa konkreettista ja käytännönläheistä tietoa siitä, millaisia vastuullisuuteen liittyviä asioita yritysten tulisi huomioida yrityskaupan eri vaiheissa. Lisäksi oppaassa käsitellään esimerkiksi hallituksen roolia ja vastuullisuuteen liittyviä verokysymyksiä. Opas on suunnattu erityisesti henkilöille, jotka haluavat saada kokonaiskuvan vastuullisuudesta osana yrityskauppoja.

New Act Governing Permitting and Construction of Offshore Wind Power within the Finnish EEZ Under Preparation

The Finnish Ministry of Economic Affairs and Employment has recently appointed a working group tasked to draft a new act that will govern permitting and construction of offshore wind power within Finland’s exclusive economic zone (the “Finnish EEZ“). The new act will provide an auction-based method for the purposes of granting project areas to interested developers as well as a new set of permits of offshore wind power projects in a situation where the existing legislation provides no functioning legal framework addressing these issues. No subsidies or other forms of State aid are planned to be offered.

Latest insights

Are Finnish Lawyers the Happiest in the World?

Article / 4 Apr 2024
Reading time 2 minutes

Implementing the Data Act without Clashing with the GDPR?

Article / 4 Apr 2024